|
|
|
GENERAL WING
|
|
| |
|
| ROADS: |
|
Chief Engineer (H), General wing is in-charge of all
State Government roads improvements and maintenance. This wing
undertakes improvements to various categories of roads viz. State
Highways Roads, Major District Roads and Other District Roads under
the following schemes: |
|
| State Government Funds |
|
| i. Part II Scheme |
| ii Special Schemes for improvements to other District
Roads in a phased manner |
| iii Mechanised Relaying of Roads. |
|
| Central Government Funds |

|
| 1. Central Road Funds Scheme |
| External Assistance |
| HUDCO Loan Assistance Scheme |
| PLAN FOR IMPROVEMENT AND REPAIRS |
|
| Improvement |
|
In the
years from 1997 - 98 to 2001 - 2002, 20,442 Km of various categories
of roads have been taken up improvement under various schemes. The
remaining 41,823 Km of roads are yet to be covered. It is estimated
that the sum of Rs. 1300.00 crores may be required to improve the
entire uncovered stretches of various categories of roads. Under the
ongoing programme of improvement of Other District Roads, during the
year 2001 - 2002, it was proposed to improve 5409.96 Km at a
cost of Rs. 250.60 crores. Likewise, 564.361 Km length of SH and
MDRs are proposed to be improved at a cost of Rs 54.39 crores, for
which proposals are under the consideration of Government. |
|
NABARD has been assisting the State Government to take
up improvement of Other District Roads till 1999 - 2000. Thereafter
they are assisting for construction of bridges and development of
rural roads only. The Government of Tamil Nadu has taken up with
Managing Director / NABARD to include improvements of ODRs also for
availing loan assistance from NABARD. |
|
| MECHANISED RELAYING OF ROADS |
|
During 1996 - 1997, due to the floods in December -
96, Government have sanctioned a sum of Rs. 150.00 crores for
permanent restoration of damaged Government roads in 8 costal
districts. These works were taken up and completed using Central
Mixing Plants, Paver and Machineries so as to ensure quality packed,
durable roads. The roads laid using the above technique, have received
public appreciation and hence it was proposed to extend this mechanized
construction method in a phased manner to other districts also. |
|
Accordingly, a sum of Rs.100.00 crores was allotted
during 1999 - 2000 for mechanized construction. Under this 1847.21
Km State Highways and Major District Roads were taken up and
completed. During
this year, proposal for Rs.154.89 crores has been formulated covering
a length of 1189 km of State Highways and Major District Roads. |
|
| CENTRAL ROAD FUND WORKS |
|
The Government of India through an Act of Parliament,
have setup a Central Road Fund with the accruals from the special
road cess levied on Petrol and Diesel. From this fund around 15 % is
distributed to the states. |
|
For the year 2000 - 2001 the GOI have allocated Rs.
67.03 crores for Tamil Nadu. |
|
The Government of India have accorded administrative
approval for Rs. 149.50 crores for 254 works under CRF scheme for
the year 2000 - 2001 in three categories viz. Widening and Strengthening,
Improvements to riding quality / Periodically Renewal and
Improvements to Accident Prone Spots on State Highways and Major
District Roads. |
|
Further, a proposal for reconstruction of
collapsed bridge across Vettar river at Km 186/6 - 8 of NH 45 A
extension ( Pondy - Nagapattinam Section) has also been approved by Government
of India. |
|
|
BRIDGES |
|
Besides having good surfaced roads, to ensure fast flow
of traffic, bridges at obstructions due to water courses, one road
crossing another road and railway level crossings are essential. |
|
To achieve such a good network, construction of
bridges have been taken up in large numbers in the recent past. |
|
New construction and reconstruction of distressed
bridges according to necessity are taken up by this wing under the
following schemes:
1. Part - II scheme
2. ROB / RUB Scheme
3. Deposit Works |

|
|
During the previous years
117 Number of Bridge works
were taken up by this wing, out of which 105 bridges have been
completed (as on date) and balance 12 number of bridges are in
progress. A sum of Rs. 7.70 crores is required to complete these
bridges. |
|
Many Bridges built during pre-independence period are
not suitable to cope up with the intensity of traffic now prevailing
and the load coming from multi-axled vehicles. They are designed as
single lane bridges. Further, most of the bridges have completed
their designed life. Of late a few such bridges have started
collapsing in succession. Hence reconstructing these bridges in a
phased manner is essential. It has been found out that the Arch
bridges in Cauvery Delta districts are prone to such collapse. A
survey has been undertaken to identify such weak and distressed bridges
which are likely to collapse. After conducting a detailed survey
, a proposal for constructing 204 bridges at an
estimated cost of Rs. 232.65 crores. Of which 94 bridges with
34 approach roads at a cost of Rs 70.2435 have been takenup with
loan assistance from NABARD. These bridge works
are under various stages of implementation. Out of
remaining 110 bridges 62 bridges on State Highways
roads at a cost of Rs.116.13 crores are proposed to be
taken up with loan assistance from HUDCO. Likewise the 48
bridges on MDRS at a cost of Rs.46.28 crores are proposed to be
taken up with loan assistance from NABARD. As regards construction of
new High Level bridges involving huge expenses, they will be
examined for taking up under BOT scheme. |
|
| PLAN
WORKS |
|
The plan works involve widening
and stregthening of roads, construction / reconstruction of bridges,
rehabilitation of distressed bridges every year under part - II
schemes according to the approval of State and Union Planning
Commissions. Under NABARD loan assistance scheme, connectivity to
villages to the nearest main roads and improvement of Other District
Roads for conveyance of agriculture products to marketing centers /
Taluk head quarters are taken-up. Similarly, improvement of Sugar
Cane Road works are carried out from Sugar Cane Cess Fund. Further,
construction / reconstruction of bridges and improvements of Radial
Roads to urban Road Safety Programmes, funds are provided jointly by
State Government and Railways for the construction of ROBs / RUBs to
replace the existing level crossings. |
|
| NON
PLAN WORKS |
|
The routine maintenance
activity involves maintenance of culverts, patch repairs, crack
sealing, road side drainage, repairing of earthen shoulders,
painting of highway signs and km stones, arboriculture and turfing,
road marking, maintenance of gang huts and store sheds, removal of
litter, debris and dead animals and replacement of damaged
retro-reflective signs etc. Further, additional maintenance activity
involves maintenance of medians, foot path repairs, minor repairs to
bridges, sub - ways and flyovers and removal of encroachments in
urban areas and maintenance of retaining / breastwalls, removal of
slips in hill areas. In addition to this, minor repairs to bridges
and ROBs / RUBs in rural and remote areas are also to be attended
under additional maintenance. The routine maintenance cost includes
cost of materials such as bitumen, road metals, gravel, paints etc.
The routine maintenance activities are done through department
personnel only. |
|
| STATUS
REPORT |
|
| The information pertaining to
roads may be viewed according to circles |
|
|
|
|